COVID-19 (Updated on 4/30/2020)

COVID-19

30 April 2020

Dear Team Members,

We hope you and your families are doing well and staying safe.

We received updated information today from key customers announcing their intentions to extend their shutdowns by one week.  Consequently, we must once again adjust our startup plans.

Plant 1: Will have no production from 5/4-5/08/2020.  There will be limited repack for service parts only starting on 5/4/2020 and those members have been contacted.  Today we started reaching out to everyone else that should report on 5/11/2020.  If you do not get a call (if you have a phone number you haven’t updated it is your responsibility to do so by calling HR) about returning on 5/11/2020 then your return to work date will be 5/18/2020.

Plant 2: All shifts and processes for Bushing have been changed also.  Bushing will begin Monday, May 11th along with Vacuum Pump.  All support members for Plant 2 are also to report on 5/11/2020.

As always, the above information is subject to change if we receive updated information from our customers.  Please continue to monitor our website, Facebook, and share with other members that may not have access to either.  We will continue to post updates.

 

Customer start-up schedules as of 30 April 2020

Toyota 5/11      Honda 5/11      Subaru 5/11      GM 5/11 & 5/24

 

Please feel free to contact HR if you have any questions.

Thank you, stay safe, and best wishes.

Senior Leadership Team