COVID-19 (Updated on 4/9/2020)

COVID-19

09 April 2020

Dear Team Members.

We hope you are doing well and staying safe.

Today we can communicate the following.

Based on our latest information from customers:

Plant 1: Will have no production from 4/13-4/29/2020.  Plan as of today is full production startup of all shifts on Thursday, April 30th.

Plant 2: Will be staggered.  As of today, Shoe will start up all shifts of production on Monday, April 20th; Bushing Inspection all shifts will start up on Friday, April 24th, Minster, Multi-Former, etc. all shifts Monday, April 27th; Vacuum Pump all shifts Thursday, April 30th.  Support members for Plant 2 will be contacted individually by HR the end of next week about their return to support production needs.  If you are a support member and do not get a phone call then you are expected to return on April 30th.

As always, the above information is subject to change if we receive updated information from our customers.  Please continue to monitor our website, Facebook, and share with other members that may not have access to either.  We will continue to post updates.

Please find below the end dates for shutdowns at our main customers.

  • Toyota: 5/1
  • Honda: 5/1
  • Subaru: TBD
  • GM: 5/1 and 5/24

Please feel free to contact HR if you have any questions.

Thank you, stay safe, and best wishes.

Senior Leadership Team